US 150 / 24 Project – (specifically, the portion on 24 in the general vicinity of ICC)

 

Scheduled work in the coming days…

 

·         Today: Shoulder work in various locations, with minimal impact on traffic

 

·         Friday: Paving the right turn lane of westbound US 24 leading up to the interchange with Village Dr./College Dr. (this is the right turn lane on the northeast side of the ICC intersection that takes drivers north onto Village Dr., the opposite direction of the campus)

 

·         Saturday: Paving the center of the US 24 intersection at the ICC entrance (traffic delays expected at this location while this work is being done – drivers should plan accordingly)

 

 

**This schedule is weather dependent and could change.**


US 150 / 24 Project – (specifically, the portion on 24 in the general vicinity of ICC)
 
Scheduled work in the coming days…
 
·         Today: Shoulder work in various locations, with minimal impact on traffic
 
·         Friday: Paving the right turn lane of westbound US 24 leading up to the interchange with Village Dr./College Dr. (this is the right turn lane on the northeast side of the ICC intersection that takes drivers north onto Village Dr., the opposite direction of the campus)
 
·         Saturday: Paving the center of the US 24 intersection at the ICC entrance (traffic delays expected at this location while this work is being done – drivers should plan accordingly)
 
 
**This schedule is weather dependent and could change.**